"The second bridge will provide consistent travel lanes and dedicated space for people biking and walking across the wash," Alison Tymkiw, Scottsdale's senior director of transportation and infrastructure, said in the city's Oct. 28 groundbreaking announcement.
Anyone who drives Thompson Peak Parkway between E. Desert Camp Drive and E. Windgate Pass Drive knows the spot. The road has four travel lanes and two bike lanes, and at the bridge over Reata Wash they squeeze down to two travel lanes and two bike lanes. That bridge is half of a crossing planned as two, and the second bridge has been on the books for as long as DC Ranch has existed.
Half a Street, Built in 2000
Minutes from Scottsdale's Paths & Trails Subcommittee meeting on Aug. 7, 2025 give the backstory. In 2000, DC Ranch built the eastbound bridge over Reata Wash as a "half street improvement" for its development. The original design also included a westbound bridge, which the City of Scottsdale was supposed to build. "That did not come to fruition," the minutes read.
The city's groundbreaking release says the same thing more plainly. When DC Ranch was developed, the city and the developer agreed to design two bridges and build only one, because traffic didn't justify a second crossing yet. The city would build the second span once the area grew into it.
Rising bicycle use is what finally made the case. According to the city, the existing bridge "has kept up with the vehicular traffic volume," and more cyclists on this stretch turned the narrowing into a safety concern for drivers and riders alike. The crossing sits on the parkway, and it also sits on DC Ranch's own path network. The community counts 47 parks linked by more than 50 miles of landscaped paths, and one of its named routes is the "Reata Wash/Thompson Peak Pkwy." route.
A Bond Project That Kept Its Number and Changed Its Dates
The bridge got its funding as Project 62 in Scottsdale's 2019 bond election, under Question 2, Community Spaces and Infrastructure. DC Ranch's project update page says community advocacy made it the only transportation project in that bond package. The schedule changed several times after the vote:
| When it was stated | What the schedule said |
|---|---|
| February 2020 | City bond report showed 2027; on March 13, 2020, City Manager Jim Thompson told the DC Ranch Community Council the project would move up to 2024 |
| March 2023 | Design in 2024, construction in 2025 to 2026 |
| July 2024 | Design funded in the FY24/25 budget, construction slated for FY25/26 |
| July 2025 | DC Ranch reported completion moved forward from 2028 to spring 2027 |
| August 2025 | 100 percent design by May 2026, construction starting summer or fall 2026, funded from the 2026/27 budget |
| October 2026 | Construction starts Monday, Nov. 2, lasting approximately 12 months |
The cost changed along with the calendar. The Scottsdale Progress reported that the bond package originally set aside $6.3 million for the bridge. At its Sept. 22, 2026 meeting, City Council approved Resolution 13778 and a construction contract with Ames Construction capped at $8,085,461.26. The full project budget is now $14.2 million. Most of it comes from the 2019 bond, and the city's 0.2% transportation sales tax covers the rest.
City Manager Greg Caton described the project as "another example of Scottsdale moving forward on projects approved by voters." In practice, voters approved it in 2019, the developer's agreement anticipated it in 2000, and the groundbreaking ceremony finally took place on Tuesday morning, Oct. 27, 2026.
What Changes on the Drive This Month
For the commute, not much changes right away. The city scheduled construction to begin Monday, Nov. 2, with crews working Monday through Friday from 7 a.m. to 5 p.m. The first phase includes:
- Salvaging and relocating native plants
- Finding underground utilities and relocating them where needed
- Drilling shafts for the bridge supports
Most of that work happens below the roadway in Reata Wash, and the city says travel lanes stay open during this phase. The contractor's staging area and a temporary nursery for the salvaged plants are located on-site.
The city runs a project hotline at 602-290-0729, and its project page is where construction updates are posted.
The city expects about 12 months of construction from the Nov. 2 start. In July 2025, DC Ranch said it had worked with the city to move the completion date up from 2028 to spring 2027.
What the Second Span Is Meant to Look Like
The westbound bridge is designed to match its 2000 counterpart in layout.
- Two 12-foot travel lanes
- A five-foot bike lane
- A five-foot sidewalk, with a separation barrier between it and traffic in the 2025 concept
When both bridges are open, the original span will carry eastbound traffic only and the new span will carry westbound traffic. Thompson Peak Parkway will then have four continuous lanes with bike lanes from Scottsdale Road to 100th Street. City staff said in 2025 that the two structures will differ but share "similar aesthetic features."
The DC Ranch Community Council reviewed the city's initial drawings and sent back specific comments in July 2026, as described on the community's update page.
- The stone should match the original bridge using DC Cobble, and imitation stone was called unacceptable.
- Jersey barriers along the full length of the bridge were called unacceptable. The board suggested dropping the sidewalk and continuing the natural path through the wash.
- Removing the arched supports under the bridge wasn't preferred, but the board called the city's cost savings understandable.
- Metal railings are acceptable if they match the original design, and the board asked that the original bridge's railings, which it described as in poor condition, also be replaced with metal.
Some of these points are community requests rather than final city decisions, especially the barrier and the sidewalk. City ordinance also requires a public art piece as part of the project. Kimley-Horn designed the bridge and Ames Construction is building it, and the city recognized both firms and the collaboration with DC Ranch at the groundbreaking.
The Rest of the Route Out of DC Ranch
The bridge work is scheduled to start just as the larger freeway project to the south has wrapped up. ADOT widened Loop 101 between Princess Drive/Pima Road and Shea Boulevard by one general-purpose lane in each direction, finishing construction in early 2026. Diamond grinding of the final surface ran from April to June 2026, and the ADOT project page reports that final striping and electrical work were completed in October 2026.
North on Pima Road, the city's Happy Valley to Jomax project covers Pima from Hackamore Drive to about 1,000 feet north of Jomax. The plans call for reconstructing the road, adding medians, bike lanes, sidewalks and trails, and replacing the HAWK crossing at Jomax with a full signal. The project page lists a winter 2026 start and a summer 2027 finish, and the city's June 2026 capital project list still showed it in design.
At Reata Wash, the city has scheduled the first phase of bridge work for below grade, with travel lanes open, and the crossing that has been two lanes since 2000 is set to carry four when both spans are done.
Long-running projects like this one tend to come up when neighbors talk about how DC Ranch is changing. Questions about how changes along your own stretch of Thompson Peak Parkway might affect your home's value are a good reason to talk with Rachel Kohn. Request an Instant Home Valuation, and Rachel can walk you through what the numbers show for your part of the community.